MFG’s FRP pile jackets restore St. George’s pier in New York

April 22, 2009 at 1:36 am Leave a comment

MFG-CP, a division of Moulded Fiber Glass Companies, supplied 20 ft stay-in-place fibre reinforced polymer (FRP) pile jackets filled with lightweight concrete to Pennmax Engineering, that are used to restore St. George’s 845 ft long pier in New York.
Made from chop strand mat and woven roving, the fibreglass reinforced thermoset composite provides resistance to abrasion while adding structural stability and impact resistance when concrete or grout is properly placed in the form.

The single seam FRP pile jackets are ¼ inch thick, have a diameter of 30 inches, are 20 ft long and weigh 400 lbs. They are chemically resistant to acids, alkalis and most solvents and are said to be durable in seawater.

Pennmax’s principal owner, John Pensiero, says: “The most critical performance spec was durability to extend the life-cycle integrity of the concrete. We chose a stay-in-place form to provide additional durability, protection, and economic efficiencies since no stripping was required. We also specified a ¼ inch form thickness to withstand ice / debris impact forces and prevent erosion of the concrete from tidal action.”

Underwater installation of FRP jackets
The MFG-CP pile jackets feature a slip-joint/ tongue-and-groove closure configuration said to make underwater assembly “easy for divers.”

Due to the 20 ft extension of the jackets in deeper water, the jackets utilised a bell-and-spigot connection, which saves installation time, allows for stacking and adds more strength structurally for concrete placement during the pumping operation.

Project Manager Ron Treveloni Jr. at Trevcon, the company performing the underwater construction, says: “Installation began by using steel reinforcing around the existing pile which was measured to fit the FRP form. Then 3-4 dock builders dropped each form in the water and set it on a floating platform to each pile location. A single diver then installs each form with the assistance of two dock builders; fastening each pile’s tongue-and-groove configuration in place.”

The restoration project, which was prompted by the return of marine borers to New York Harbor causing the fast deterioration of timber piles, began in October 2008 and is scheduled for completion in summer 2009. The New York City Economic Development Corporation (NYCEDC) awarded the contract to restore the pier piles through national general contractor Turner Construction of New York.

Reinforced Plastics

Advertisements

Entry filed under: Staten Island, Working Waterfront. Tags: , , .

NY’s Hudson Valley marks historic 1609 voyage OPM Lands in Sheepshead Bay

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out / Change )

Twitter picture

You are commenting using your Twitter account. Log Out / Change )

Facebook photo

You are commenting using your Facebook account. Log Out / Change )

Google+ photo

You are commenting using your Google+ account. Log Out / Change )

Connecting to %s

Trackback this post  |  Subscribe to the comments via RSS Feed


Going Coastal NYC

Connecting People to Coastal Resources

%d bloggers like this: